I UNDERSTAND

Stanway viaduct appeal

Help us save our viaduct!
The GWRT needs to raise £1.5m to undertake urgent repairs to Stanway Viaduct.

History of the viaduct

The building of the viaduct

Standing proud just north of Toddington station, Stanway Viaduct has transported passengers across the valley between Toddington and Broadway since 1904.

Acting as the railway's gateway to Worcestershire, this 656 feet long structure spans 15 arches and stands nearly 50 feet high.

Following closure of the original GWR mainline in 1976, Stanway Viaduct lost its track in 1979, seemingly never to see another train again. However, in 2005, intrepid GWSR volunteers, determined to reach Broadway station, re-laid a single track across the viaduct.

Thanks to their determination, Stanway finally carried passengers once again in 2010, with trains initially travelling as far as Laverton before the GWSR reached Broadway in 2018.

What's happened?

Pier damage due to water ingress

The structure was built with a waterproof layer of asphalt below the ballast. Water percolating through the ballast should enter catch pits and then travel via drainage pipes exiting within the arch soffits.

Recent evidence showed that the waterproofing layer had failed and so the structure had suffered from the effects of water penetration over many decades.

Unless halted, the structure will continue to deteriorate to a point where it can no longer safely carry the loads and stresses imposed by our trains.

Essential repairs were carried out in 2021 and 2022 but funds did not permit the root cause of water penetration to be fully addressed at that time.

In late 2023/ early 2024, the waterproofing was repaired, and the viaduct is now drying out. Work to repair the brickwork is still needed, and is in the process of being planned out.

What has been done?

Phase 1 - COMPLETE

The waterproofing needed replacing across the length of the viaduct. This required the current track and ballast to be removed, allowing a concrete layer to be installed which ensures that water flows towards the catch pits. Two waterproofing layers would then be applied before the ballast and track could be replaced. This would cost in excess of £350,000, the GWRT’s first fundraising target.

The completed stabilising and waterproofing

Thanks to the generosity of everyone who donated to the Viaduct Appeal, Phase 1 was fully funded by donations and completed during the winter of 2023/2024. Following closure of the line in November 2023, volunteers from the GWSR removed the track over the viaduct within a week, allowing the contractors to make a quick start.

Removal of the ballast uncovered a fault in the brickwork running along the entirety of the parapets on either side of the viaduct, and an engineering resolution was quickly sought. An additional £200,000 was provided from the Trust's reserves to complete the repair, minimising the delay and allowing the waterproofing work to continue.

The Viaduct reopened to passenger traffic on 29 March, just in time for the GWSR’s full summer season.

What needs to be done?

Phase 2

In addition to waterproofing the structure, the brickwork damaged by decades of water ingress needs to be repaired.

Scaffolding on the viaduct in 2022

This includes the spandrels, the arch soffits, the parapets and the brickwork of the nine piers not repaired previously. These works require skilled bricklayers, so the intention is to spread the work over approximately 3 years.

A further challenge during this phase is the provision of safe access to enable the bricklayers to reach all parts of the structure. This will require scaffolding nearly 50 feet in height.

Phase 2 is estimated to total £1.2 million - £400,000 in each of the three years anticipated to be required to complete the work.

The majority of the remedial work on the viaduct will be carried out by specialist contractors working for the GWSR, with the track work being undertaken by the railway's volunteer track maintenance team.

For more information about the damage to Stanway Viaduct and the necessary remedial work, check out our FAQ document.

How you can help

Every donation, big or small, will help us preserve this historic structure.

Whilst Phase 1 has completed, we continue to fundraise in anticipation of Phase 2.

The timeline for Phase 2 is currently unknown whilst plans are confirmed.

Ways you can donate

Stanway Viaduct featured on GWSR marketing
  • Head to our online donations portal by clicking here
  • Fill out the appeal leaflet and return it to:
    Appeal Administrator, GWRT
    Churchward House
    Winchcombe Railway Station
    Station Approach
    Winchcombe, Cheltenham
    GL54 5LD
  • Visit our Trust Office at Toddington Station.

All monies donated to the Viaduct Appeal will be held by GWRT in a restricted fund, used to pay invoices provided by contractors to the GWSR.